Yes. American Fork requires a permit for nearly every permanent business sign. Size and height depend on your parcel's zoning and sign overlay zone, and monument or pylon signs must be approved with the site plan. NOTATEK prepares the drawings and handles the submittal.
Yes. In American Fork, permanent business signs such as wall letters, lighted cabinets, monument signs and pylons need a city permit before they go up. What you are allowed to build depends on your parcel's zoning and the sign overlay zone it sits in, and freestanding signs also have to be approved as part of the site plan. If you hire NOTATEK, we prepare the permit drawings and handle the submittal.
Last verified: November 17, 2026. This is a plain-English summary of the city's posted sign ordinance, not legal advice. Rules change, so check with American Fork City before you order a sign.
Which American Fork code section covers signs?
American Fork's sign rules are in Section 17.5.128, "Signs and Advertising Structures," of the American Fork City Development Code (Title 17). The city links the full Development Code and a copy of its Sign Ordinance from its Building Department checklists and ordinances page. The posted copy is Ordinance No. 2013-03-10, and the section has been amended since, so treat it as a starting point and confirm the current text with the city.
You may also see a new Chapter 17.20 mentioned for signs. The Planning Commission's April 20, 2022 agenda included a hearing on amending the sign section, along with a draft ordinance that would repeal Section 17.5.128 and adopt a new Chapter 17.20 on signs. We could not confirm that the rewrite was adopted. In the indexed copy of the code we reviewed, signs are still in Section 17.5.128 and Chapter 17.20 covers annexation. Ask the city which version applies before you design to either one.
Which signs need a permit in American Fork?
Section 17.5.128 allows temporary and permanent accessory signs in all zones "upon the acquisition of a permit." The list of signs that need no permit is short, and none of it covers a typical business sign.
| Sign type | Permit needed? | Notes from the posted ordinance |
|---|---|---|
| Wall (facia) and canopy signs, including channel letters | Yes | Area is set by the size of the building face or tenant frontage (Chart 17.5.128-A); up to two signs per building street frontage; no more than 15 inches off the wall |
| Projecting signs (General Commercial and Industrial zone) | Yes | One per tenant, up to 30 sq ft; at least 12 ft above the ground and 14 ft above a driveway; never over a public right-of-way |
| Monument signs | Yes, plus site plan approval | Up to two faces of 60 sq ft each |
| Pylon signs | Yes, plus site plan approval | 35 ft maximum height; face area set by street or freeway frontage (Charts 17.5.128-B and C) |
| Real estate, political and produce signs | No | Size and removal limits still apply |
| Unlighted nameplates for professionals or home occupations | No | 2 sq ft maximum |
| Government and public information signs | No | Traffic, street, safety and similar signs |
If you are unsure about something else, such as window graphics or a grand-opening banner, ask the city before you install it.
Does zoning affect what sign I can put up in American Fork?
Yes, more than anything else. As our American Fork page puts it, an exterior sign here is a permitted, inspected, electrically connected piece of building equipment, and its size, height, setbacks and illumination are governed by the zoning for your parcel. Section 17.5.128 layers two sign location overlay zones on top of the base zones:
- I-15 Corridor Sign Location Zone. Mapped along the freeway. Signs here need prior Planning Commission approval. Up to 20% of a wall sign's face may rise above the roof line, but no more than 15 feet above it. A freestanding pylon needs at least 5.5 contiguous acres and 500 feet of I-15 frontage.
- General Commercial and Industrial Sign Location Zone. Covers the CC-1, CC-2, GC-1, GC-2, SC-1 and I-1 zones outside the I-15 corridor. Wall signs may not extend above the roof line, a pylon generally needs at least 150 feet of street frontage, and a monument sign must be at least 100 feet from any other monument, pylon or project sign on the same or an adjacent parcel.
Electronic message displays are prohibited except where Section 17.5.128 specifically allows them, such as a limited share of the face on certain pylon and project signs. Billboards are not allowed except under specific code provisions. On top of the city's rules, a landlord's sign criteria are often stricter than the ordinance, and they change the design more often than the code does.
How do I get a sign permit in American Fork?
This is the order we run an American Fork sign project in. Steps 4 and 5 are where the city comes in.
- Send the basics. Your address, logo files and, if you lease, the landlord's sign criteria.
- Site survey. We check the mounting surface, power, sightlines and any landlord or city constraints, and confirm which zone and overlay zone apply.
- Design to the strictest rule. We size the sign to the code charts and the landlord criteria, then get landlord sign-off on the drawings.
- Site plan check for freestanding signs. When a commercial or industrial project needs Planning Commission site plan approval, its signage plan is part of that review, and a monument or pylon sign is not permitted unless its location and design were approved with the site plan. In the indexed code we reviewed, a sign requested after site plan approval goes through a sign permit with administrative review by city staff.
- City submittal. We prepare the drawings and specifications and file them. The city's Building Department page says some projects first need a Zoning Clearance Letter from Planning and Zoning, filed through the city's CityInspect portal, before the building permit.
- Fabrication. The sign is built in our shop at 1584 S 580 E in American Fork.
- Installation and inspection. Our own crew mounts and wires it, and the electrical inspection is part of our scope.
How long does a sign permit take in American Fork?
The posted Section 17.5.128 does not publish a review deadline for sign permits. The 2022 draft rewrite proposed a fixed staff review period, but since we could not confirm it was adopted, do not plan around it. Review time depends on whether your sign needs Planning Commission or site plan approval, how complete the drawings are and the city's workload, so ask Planning when you apply.
For the whole project, most of our electric sign jobs run about 4 to 8 weeks from approved design to installation, driven mainly by permitting and fabrication. A single channel-letter set is faster, and a large monument sign takes longer. Because our shop is ten minutes away, a reviewer's request to change a dimension or an inspector's question is a short trip for us, not a rescheduled week.
What does a permitted sign cost in American Fork?
These are our typical installed ranges for the sign itself. We give a firm quote after a quick site review. City permit fees are set by the city, so ask Planning for the current fee schedule.
| Sign type | Typical installed range |
|---|---|
| Storefront channel-letter set | About $2,000 to $8,000 |
| Illuminated cabinet sign | About $1,500 to $5,000 |
| Freestanding monument or pylon sign | Roughly $5,000 to $25,000+ |
For freestanding work in particular, start early, because monument and pylon placement can be tied to the site plan. You can see finished examples on our monument sign page.
Frequently asked questions
Do I need a sign permit in American Fork, Utah?
Almost always, for a permanent business sign. Section 17.5.128 of American Fork's Development Code allows temporary and permanent accessory signs in all zones only after a permit is issued. The exemptions are narrow: real estate, political and produce signs, small unlighted nameplates, and government or public information signs. Rules change, so check with the city before you order a sign.
Who pulls the sign permit, me or the sign company?
On NOTATEK projects, we do. Drawings, submittal and the electrical inspection are part of our scope, the same as on every sign we build. Your part is to send the address, your logo files and, if you lease, the landlord's sign criteria, then approve the drawings. Being based in American Fork means follow-up questions from the city get answered quickly.
Can I hang a temporary banner while my permanent sign is being built?
Possibly. American Fork's posted sign ordinance prohibits permanent banner signs and portable signs, but allows them temporarily for a new or relocated business until the permanent signs are installed, for no more than ninety days. Other temporary signs are prohibited unless another part of the Development Code allows them. Confirm with the city before you hang one, because rules change.
Can my American Fork sign have an electronic message display?
Only where the code specifically allows it. Section 17.5.128 prohibits electronic display signs except as that section permits, and it allows them mainly as a limited share of the face on certain pylon and project identification signs. A typical storefront wall sign does not qualify. Ask the city about your parcel before you budget for a digital display, because the rules change.
Is Chapter 17.20 the American Fork sign code?
Not as far as we could confirm. A 2022 draft ordinance proposed moving the sign rules into a new Chapter 17.20, but we found no record that it was adopted, and the indexed code we reviewed still places signs in Section 17.5.128. Ask American Fork Planning which version governs your application before you design a sign to either one.